Unknown: Turbocor, the world's first magnetic bearing oil-free centrifugal compressor for air conditioning applications from Danfoss: engineering tomorrow. Safety precautions must be observed during the installation, start-up and service of the compressor due to the presence of pressure and voltage hazards.
Only qualified and trained personnel should install, start-up and service Danfoss Turbocor compressors. This step-by-step
service tutorial will guide you through the removal of the Danfoss Turbocor 342 Inverter and installation of the 613 Inverter on major revision F and earlier TT300 and TG230 compressor models. The function of the inverter is to convert the high
models. The function of the inverter is to convert the high DC voltage input to a variable frequency three-phase AC voltage output to the motor to turn the shaft at the required speed and torque. The backplane sends 24 volts DC and control signals to
torque. The backplane sends 24 volts DC and control signals to the inverter from the BMCC. In return, the inverter sends motor current, temperature and DC voltage information to the BMCC via the backplane. The need to change the inverter may arise when inverter-related faults are occurring. Refer to
troubleshooting outlined in the service manual or the TurboTool app. Before performing any service on a Danfoss Turbocor
app. Before performing any service on a Danfoss Turbocor compressor, electrical power must be isolated. Turn off the mains input power to the compressor and lockout-tagout the mains disconnect. Confirm that the AC voltage is isolated. Wait at
disconnect. Confirm that the AC voltage is isolated. Wait at
least 20 minutes for the DC bus capacitors to discharge. Remove
the top cover, taking care not to touch any components underneath.
Then, using an appropriately rated voltage meter, check the DC bus bars for DC voltage level. If the voltage is above five volts DC, wait five minutes and recheck until voltage is below five volts DC.
ESD precautions must be taken to prevent possible damage to static-sensitive components. A grounding wrist strap must be
static-sensitive components. A grounding wrist strap must be worn when handling ESD sensitive components. For F series compressors, disconnect the soft start temperature cable. Cut and
remove the cable ties that bind the harnesses. Disconnect the
soft-start ground wire by removing the nuts and mains input ground wire from the ground posts on the compressor housing. Remove the fasteners that secure the soft-start
housing. Remove the fasteners that secure the soft-start mounting bracket to the compressor. Then lift the soft start and turn it over. Unplug the cable connectors from the soft-start board and remove the soft-start assembly. Remove the
fasteners from the AC-DC cable harness on the AC input fuses.
Remove the fuse blocks and mylar insulator from the mains terminal. Remove the screws that retain the mains terminal block.
terminal. Remove the screws that retain the mains terminal block.
Place the terminal block aside. Remove the bolts from the SCR DC bus bars. Disconnect the cables from the motor
bus bars. Disconnect the cables from the motor winding thermistor terminals, DC-DC, inverter, and SCR temperature sensor. Remove the snubber
capacitors. Remove the nylon nuts and pressure relief foil
capacitors. Remove the nylon nuts and pressure relief foil at the base of the compressor.
Remove the DC bus capacitors as an assembly. Remove the
insulating mylar from the inverter. Disconnect the
compressor cable harness from the suction and discharge sensors and IGV motor.
Remove the bolts and cover tubes that connect the motor bus bars to the inverter. Remove the motor bus bars from the high- power feedthroughs. To remove the DC-DC, loosen the back screws
power feedthroughs. To remove the DC-DC, loosen the back screws and remove the front screws. Carefully lift and pull the DC- DC out and away from the inverter plate. The thermal
paste between the DC-DC and the inverter cooling plate may stick.
Remove the fasteners that secure the inverter to the compressor main housing. Follow standard refrigerant recovery procedures
main housing. Follow standard refrigerant recovery procedures prior to removing the inverter. Remove the inverter assembly with the SCR manifold. Carefully peel back the SCR manifold insulation and remove the two fasteners. Place the SCR
manifold aside for reuse with the new inverter. Apply O-lube
to the smallest O-rings and install them into the SCR cooling manifold. Install the SCR manifold to the 613 inverter
cooling manifold. Install the SCR manifold to the 613 inverter cooling manifold using the two fasteners and torque to seven Newton meters. Clean the O-ring grooves in the compressor
Newton meters. Clean the O-ring grooves in the compressor housing. Apply O-lube to the inverter O-ring and place the
housing. Apply O-lube to the inverter O-ring and place the O-ring in the compressor housing groove. Install the small O-ring into the motor cooling port. Remove the backing material from the cooling manifold of the new inverter. Handle carefully to prevent damage to the sealing surface of the inverter
manifold. Route the SCR temperature sensor cable
manifold. Route the SCR temperature sensor cable underneath the manifold before installing the inverter.
Carefully install the inverter on the compressor housing.
Install the inverter screws using a diagonal pattern.
Tighten first at three Newton meters, then to eight Newton meters. Check all screws. Before continuing with assembly, leak-
meters. Check all screws. Before continuing with assembly, leak- test and begin to evacuate the compressor. Start the back four DC-DC screws on the inverter plate and install the DC-DC with the front four screws already in the DC-DC. Starting from the
middle of the DC-DC, tighten the DC-DC screws to 0.5 Newton meters, four inch pounds. Reconnect the SCR temperature sensor. Route
the compressor cable harness between the inverter and SCR manifold and connect to the discharge sensor, IGV motor connection, and the suction sensor. Install the new manifold insulator mylar on the DC bus capacitor assembly over the last two negative busbar contacts. Place the DC bus
capacitor assembly on the compressor over the inverter.
Loosely install the snubber capacitors and SCR busbar bolts.
Tighten the snubbers, starting from the capacitor side and working toward the DC-DC to seven Newton meters. Tighten the
SCR busbar bolts to 10 Newton meters. Underneath the
capacitors, install the membrane and nylon nuts. Place the new motor busbars in correct location. Loosely install the bolts to the high-power motor feedthroughs and to the inverter with the copper tubes in place. Tighten the bolts to the
inverter to 14 Newton meters. Then tighten the high-power motor feedthrough bolts to 14 Newton meters. Connect the cable harnesses to the inverter, DC-DC and motor thermistor terminals.
Connect the AC-DC harness to the DC bus. Install the terminal block over the housing standoffs and place the mylar in the
middle of the terminal block. Install the 3 fuse assemblies to the terminal block and torque to four Newton meters. Install
the three AC cables in correct order on the fuse input to the SCRs. Torque to five Newton meters. Holding the soft start
SCRs. Torque to five Newton meters. Holding the soft start by its frame over the SCRs, connect the AC-DC cable harness and gate cable.
Turn the soft start over and secure it to the motor tower.
Torque to five Newton meters. Connect the soft start temperature cable. Route the soft-start ground cable down
temperature cable. Route the soft-start ground cable down to the ground post, install the nut over the top and tighten to 10 Newton meters.
Use a cable tie to bundle the wires above the DC-DC and behind the soft start.
Inspect all connections. Ensure all fasteners are secure and all components are properly installed. Install the top side cover. Install the mains input cover before applying power.
cover. Install the mains input cover before applying power.
Apply power to the compressor and verify operation. This
concludes the Danfoss Turbocor TT300 and TG230 inverter replacement presentation. For more information on Danfoss
replacement presentation. For more information on Danfoss Turbocor products and service documentation, please visit us online at Turbocor.com.
Loading video analysis...